This project includes construction of new raised intersections on 108th and 110th Avenues NE, at NE 6th Street in downtown Bellevue. It aims to improve safety and accessibility to the transit center for both pedestrians and buses. The raised intersections will provide a seamless street crossing for pedestrians traveling from the East Link light rail station and the Bellevue Transit Center. They are located along the future Grand Connection, a signature, pedestrian-focused corridor through the heart of downtown Bellevue.
Benefits
The project includes the following enhancements:
- Raised, concrete intersections
- Replace existing sidewalks
- Replace traffic signal system
Schedule
- Design Start: Spring 2021
- Design Complete: Fall 2022
- Construction Begins: Winter 2023
- Construction Complete: Summer 2023